1 Monday 1998 :
Goddard Space Flight Center
Building 5, Clean Room
Tasks Completed:
- EUV spectrometer removed from pumps
- EUV spectrometer vacuum valve sealed for flight
- SEH-3 instrument assembly installed into flight canisters
- SEH-3 CGSE checkout began with ACCESS
- SEH-3 instrument reservoir pressure checks
2 Tuesday 1998 :
Goddard Space Flight Center
Building 5, Clean Room
Tasks Completed:
- SEH-3 Motorized Door Assembly installed/Mechanical integration complete
- SEH-3 support electronics installed into flight canister
- SEH-3 blankets installed
- SEH-3 instrument canister installed onto bridge
Photos:
- SEH-3 Pressure Proof Test (36K)
- Sometimes the GSFC crew needs a little persuasion... (73K)
3 Wednesday 1998 :
Goddard Space Flight Center
Building 5, Clean Room
Tasks Completed:
- Isolation checks completed
- Electrical hookup to shuttle avionics for testing
- Command capability verified at ground station
4 Thursday 1998 :
Goddard Space Flight Center
Building 5, Clean Room
Tasks Completed:
- Command and Data testing begins
- CGSE connections with ACCESS verified and tested
5 Friday 1998 :
Goddard Space Flight Center
Building 5, Clean Room
Tasks Completed:
- SEH-3 electrical turn on with avionics
- SEH-3 operations functional test completed
- Video test completed
- Integration completed successfully and on time!!
|